[00:00:00] Speaker 02: 21-084, BGT Holdings versus United States. [00:00:05] Speaker 02: Mr. Johns, whenever you're ready. [00:00:09] Speaker 00: Good morning, and may it please the court. [00:00:11] Speaker 00: Thank you, Chief Judge Prost. [00:00:13] Speaker 00: My name is Milton Johns, and I argued this morning on behalf of BGT Holdings, LLC. [00:00:20] Speaker 00: Excuse me. [00:00:21] Speaker 00: Because the matter is fully briefed, there are three specific areas I would like to call to the panel's attention. [00:00:30] Speaker 00: regarding the arguments. [00:00:32] Speaker 00: And I think that we must depart initially from the understanding that this is an appeal of the decision made on a 12b6 motion to dismiss, which under normal standards, disputed issues should be construed favorably to the plaintiff and all reasonable inferences drawn in favor of the plaintiff. [00:00:59] Speaker 03: Mr. Johnson, this is Judge Bryce, and if I could interrupt you for just a second, and I only want a very summary answer here, because I don't want to take up a lot of your time. [00:01:09] Speaker 03: But going to the merits of this case, I know we're not there yet, but on the merits of the underlying contract dispute, is it the government's position that there was some kind of contract provision that required cost savings for government furnished equipment? [00:01:30] Speaker 00: Your Honor, we understand that that was a post-contract negotiation attempt by the contracting officer to... There's nothing in the contract that entitles the government to a cost savings. [00:01:44] Speaker 03: Is that what you're saying? [00:01:45] Speaker 02: That's correct, Your Honor. [00:01:47] Speaker 02: All right. [00:01:47] Speaker 03: That's fine. [00:01:48] Speaker 03: Thank you. [00:01:49] Speaker 02: I actually had a question similar to the one Judge Bryson asked, just trying to understand the contract. [00:01:56] Speaker 02: Did the contract value account [00:02:00] Speaker 02: for the GFE being provided? [00:02:02] Speaker 00: Yes, Your Honor. [00:02:06] Speaker 00: The contract as negotiated included those six GFE elements. [00:02:12] Speaker 02: So if the government had indeed provided all the GFE, was it then entitled under the contract to subtract that value? [00:02:21] Speaker 00: No, Your Honor. [00:02:25] Speaker 02: So I guess I'm a little unclear on what this cost savings [00:02:29] Speaker 02: demand is all about? [00:02:34] Speaker 00: Well, Your Honor, the facts as we understand and believe them were that the contracting officer was attempting to save money after the contract had been issued and that if BGC Holdings was not willing to [00:02:55] Speaker 00: reduce some of those prices or reduce the cost, fine cost savings if you would, that the indication was they would remove pieces of government furnished equipment and that BGT would have to go buy those pieces on the commercial market instead, which is what happened in this case. [00:03:18] Speaker 02: You know, I've never contracted with the government, but is this comment that, you know, we have a contract, there's a price agreed to, everything's agreed to. [00:03:26] Speaker 02: And then after that, the government comes in and says, Hey, we'd like to save a little more money. [00:03:30] Speaker 02: Um, you got to find a way to do it. [00:03:34] Speaker 02: Is this a common practice as far as you know, in your experience? [00:03:39] Speaker 00: Well, your honor, I've been involved in government contracting for 35 years and, uh, I would be incorrect if I said I'm, I never saw this happen. [00:03:48] Speaker 00: But typically it is, it occurs in the province of a clause that allows, you know, for instance, value engineering to find cost savings and so forth. [00:04:01] Speaker 00: It is, and this is anecdotally my experience based on 35 years, very unusual for a contracting officer essentially to say if you don't lower the price, [00:04:14] Speaker 00: you know, I'm going to take away some part of it to increase your prices. [00:04:20] Speaker 00: Okay. [00:04:20] Speaker 02: Sorry to interrupt. [00:04:21] Speaker 00: Why don't you proceed with your argument? [00:04:23] Speaker 00: Thank you, Your Honor. [00:04:26] Speaker 00: So the three main points related to the amended complaint are that there was a constructive change in the contract that the government failed to make an equitable adjustment [00:04:41] Speaker 00: and then finally that the government breached its duty of good faith and fair dealings. [00:04:46] Speaker 00: It's important to note that those are all alternative theories for the same essential contractual injury, which was the removal of the government furnished equipment. [00:04:58] Speaker 00: So they are all alternative and not cumulative theories. [00:05:03] Speaker 00: I think what's important under the first theory and the court and [00:05:09] Speaker 00: and the government spends most of its time looking at is this notion that a changes clause in a contract can ex ante eliminate the contracting company's ability to raise the claim of a constructive change or as we put forward, waiver or ratification. [00:05:33] Speaker 00: The waiver and ratification claims are [00:05:37] Speaker 00: are also in the alternative. [00:05:40] Speaker 00: One being that the contracting officer's representative, Ms. [00:05:45] Speaker 00: Ornesti, was simply communicating a decision that had been made by the contracting officer or in the alternative that she acted with implied authority and then the contracting officer, Mr. Stefano, ratified those actions. [00:06:02] Speaker 00: And so I think that the Winter case, [00:06:06] Speaker 00: really is instructive because there appears to be no specific case law citation provided by the court or the government that says that a changes clause forecloses legal remedies or legal arguments such as waiver and ratification. [00:06:25] Speaker 00: In the winter case, this court specifically considered a contract that had a very similar changes clause. [00:06:36] Speaker 00: And, in fact, the court said that implied authority was an issue to be considered. [00:06:43] Speaker 00: The court found that there was no implied authority there. [00:06:48] Speaker 00: But the court did go on to say that there was a ratification of the actions that were taken. [00:06:55] Speaker 00: even in spite of this changes clause. [00:07:00] Speaker 02: You talked about, I'm sorry to interrupt, but time is short. [00:07:03] Speaker 02: So you've got the breach of contract, the duty of good faith. [00:07:07] Speaker 02: Is it your view that they all, at least at this stage in the 12b6 context, do these all rise and fall together in your view? [00:07:17] Speaker 00: Well, Your Honor, they are alternative. [00:07:22] Speaker 00: The court has dismissed all three counts. [00:07:24] Speaker 00: They were pled as separate counts. [00:07:27] Speaker 00: And they were pled in the alternative. [00:07:29] Speaker 00: But the court dismissed each of the three. [00:07:33] Speaker 00: And so we have appealed the dismissal of each of those three counts. [00:07:38] Speaker 00: But they're really three different theories to achieve the same remedy. [00:07:47] Speaker 00: which is the accounting, the adjustment for the removal of the government furnished equipment from the contract. [00:07:54] Speaker 03: This is Judge Bryson. [00:07:55] Speaker 03: Could I ask you about your breach of contract theory? [00:07:58] Speaker 03: And I gather your breach of contract theory is not that there was a breach by the withdrawal of the government furnished equipment, but rather that the breach came with the failure to grant an equitable adjustment. [00:08:11] Speaker 03: And the government's answer to that is that [00:08:15] Speaker 03: The only obligation that the contracting officer had with respect to an equitable adjustment is to consider, I think that's the language in the regulation, an equitable adjustment and they said the contracting officer did that. [00:08:33] Speaker 03: First part of the question is do you agree that that is the [00:08:39] Speaker 03: pertinent language from the regulation that governs this, that the contracting officer must consider an equitable adjustment. [00:08:47] Speaker 03: And second part of the question is what do you think, if you're familiar with any authority on this, none are cited in the briefs, but what do you think consider in this context entails? [00:09:02] Speaker 03: What degree of responsibility on the part of the contracting officer is carried with the term consider? [00:09:11] Speaker 00: Yes, Your Honor. [00:09:12] Speaker 00: And the clauses that are at issue, in my review of the applicable clauses, I think the words that are used is shall. [00:09:23] Speaker 00: So in 245-1, which talks about the removal of government furnished equipment, we concede that there's no breach of contract for [00:09:36] Speaker 00: simply removing the GFE. [00:09:39] Speaker 03: Right, it says shall consider, and shall certainly has some force, but the key word for me at least is the word consider. [00:09:49] Speaker 03: So I'm wondering whether you have any kind of authority or basis for suggesting that that word means something other than what the government attributes to it. [00:10:04] Speaker 00: Your Honor, in 52-245-1i, it actually says equitable adjustments shall be made and not considered. [00:10:16] Speaker 00: I don't believe the word considered is in those clauses. [00:10:25] Speaker 03: I'm looking at 245-1d2 Romanet 1. [00:10:31] Speaker 03: D3 Romanet 2, which are specifically directed to the withdrawal of government property. [00:10:37] Speaker 03: And one of them says if the property is not delivered to the contractor, which of course happened here, the contracting officer shall upon the contractor's timely written request consider an equitable adjustment. [00:10:50] Speaker 03: And 245.1 D3 Romanet 2 says upon completion of any action under the paragraph [00:11:01] Speaker 03: And the contracting officer shall consider an equitable adjustment to the contract. [00:11:08] Speaker 03: So that's the language that I was focusing on. [00:11:12] Speaker 03: Once again, do you have any, what is your argument, assuming we conclude that that's the operative language, what is your argument with respect to the obligation that is conferred by the word consider? [00:11:28] Speaker 00: Well, Your Honor, I think a consider certainly would imply that there is still a duty of good faith and fair dealing. [00:11:36] Speaker 00: And I think that that consider would require something that's not arbitrary and complete and capricious and, you know, certainly not in the context of an approach to attempt to reduce the contract price by removing [00:11:56] Speaker 00: these items. [00:11:59] Speaker 00: I believe when you read that clause in conjunction with sub I, where it specifically talks about the equitable adjustment, that paragraph I think goes further to say shall made. [00:12:12] Speaker 00: And I agree that D says shall consider. [00:12:16] Speaker 00: I think we have to read that in conjunction with sub I when it specifically talks to the equitable adjustment and says shall be made. [00:12:28] Speaker 02: All right. [00:12:28] Speaker 02: I think we heard your buzzer, right? [00:12:32] Speaker 02: Why don't we hear from the government and we'll reserve your rebuttal time. [00:12:39] Speaker 02: Mr. Kushner? [00:12:43] Speaker 01: Thank you, Your Honor, and may it please the Court. [00:12:46] Speaker 01: Contract interpretation is a question of law, and when the plain language of a contract precludes the plaintiff's theory of liability, a trial court can dismiss the claim under Rule 12b6. [00:12:56] Speaker 01: The simple and well-established principle should lead to affirmance in this case. [00:13:03] Speaker 03: Let me interrupt you right at the outset and let's pick up where we left off with your opposing counsel. [00:13:10] Speaker 03: Is it the government's theory here that the government can promise in the contract to provide government furnished equipment even though that may be 90% of the costs [00:13:24] Speaker 03: that the contractor would otherwise incur. [00:13:28] Speaker 03: And then the government can withdraw that equipment after the contract is signed. [00:13:38] Speaker 03: And all it owes to the contractor is that the contracting officer consider an equitable adjustment and that the contracting officer has complete discretion as to whether to grant the equitable adjustment or not. [00:13:56] Speaker 03: Because that's what I took away from page 27 of your brief. [00:13:59] Speaker 03: That sounded like the argument you were making. [00:14:01] Speaker 03: I just want to make sure that I'm not misreading your position. [00:14:05] Speaker 01: Certainly. [00:14:07] Speaker 01: Certainly, Judge Bryson. [00:14:08] Speaker 01: And before I answer the question, I do want to note that the argument with respect to the shall consider language and FAR 52.245-1, that is not an argument that BGT raised. [00:14:23] Speaker 01: If they had raised this argument, [00:14:25] Speaker 01: I think our response would have been that under this FAR provision, the contracting officer does have an obligation to consider a request for an equitable adjustment in good faith. [00:14:37] Speaker 01: There are other FAR provisions that could be implicated in this issue as well. [00:14:42] Speaker 01: For instance, FAR 52.243-1. [00:14:46] Speaker 01: which is another FAR provision incorporated by reference into the contract. [00:14:50] Speaker 01: And that provision does say that the contracting officer shall grant an equitable adjustment under certain circumstances. [00:14:58] Speaker 01: So there may be a contractual obligation to provide an equitable adjustment. [00:15:04] Speaker 01: There certainly is a contractual obligation to consider such an adjustment in good faith. [00:15:10] Speaker 01: But, you know, in this respect, I do want to point to court's attention [00:15:14] Speaker 01: later in 52.245-1 in subsection I where it says that any equitable adjustment shall be made in accordance with the procedures of the changes clause, which is another way of saying any equitable adjustment can only be made upon the direction of an authorized government agent who is the contracting officer. [00:15:41] Speaker 01: And so, in this case, this is part of the reason why an equitable adjustment is not available to DGT. [00:15:48] Speaker 01: There is no allegation that the contracting officer modified the GFE provision as the changes clause requires. [00:15:56] Speaker 03: You know, here's what I am having trouble with with respect to your position. [00:16:02] Speaker 03: Normally, in these situations, a modification is made [00:16:07] Speaker 03: that imposes additional burdens on the contractor, and the contractor ultimately asks for an equitable adjustment thanks to the modification. [00:16:17] Speaker 03: But here, and in that situation, it makes sense to say that if the contracting officer didn't authorize the modification, then the contractor should not do the work until it gets the authorization of the contracting officer. [00:16:31] Speaker 03: But in this situation, what you've got is the government acting unilaterally [00:16:37] Speaker 03: not saying to the contractor, you must do this work, but unilaterally withdrawing some of the equipment from the project. [00:16:46] Speaker 03: And what is the contractor supposed to do in that situation if the withdrawal was not expressly authorized by the contracting officer? [00:16:58] Speaker 03: The contractor doesn't have the choice of simply saying, I'm not going to do the work. [00:17:06] Speaker 01: So we are not suggesting that if the modification of the GFE provision here was done properly, that is done by the contracting officer in writing and signed by the contracting officer as the changes clause requires, we're not suggesting that in that situation a contractor like BGT would have no remedy for an equitable adjustment. [00:17:28] Speaker 03: I understand that, but my question is suppose that as in this case the contracting officer did not [00:17:36] Speaker 03: authorized the withdrawal of the government property, but it was done by someone else. [00:17:42] Speaker 03: What's the contractor supposed to do in that situation? [00:17:45] Speaker 03: If you were the lawyer for the contractor, what would you tell them to do? [00:17:49] Speaker 03: Walk off the job. [00:17:53] Speaker 01: Certainly. [00:17:53] Speaker 01: So if I was the lawyer for the contracting officer, the first thing I would do is look at the changes clause, which not only requires any modifications to be done by the contracting officer, [00:18:03] Speaker 01: but it even sets out the identity of the contracting officer and their contact information. [00:18:10] Speaker 01: And what I would do is I would tell BGT to go back to whatever unauthorized government agent gave them the directive, in this case the procurement manager, and ask that individual for an order issued and signed by the contracting officer. [00:18:27] Speaker 03: And if they said that's not something we're going to do, we're just going to take the property and not provide the government furnished property, then what do you do? [00:18:39] Speaker 01: So I'm sorry, the question is if the unauthorized government agent refused to refer this matter to the contracting officer? [00:18:50] Speaker 01: It would be unclear what would happen in that circumstance, but that is not what happened here. [00:18:55] Speaker 01: There is no allegation that DGT went to Ms. [00:18:58] Speaker 01: Onesti, the procurement manager, and said, look, we really have to get an order from the contracting officer himself. [00:19:05] Speaker 01: Instead, the allegation here says that once Ms. [00:19:08] Speaker 01: Onesti allegedly told DGT that they can no longer use these particular pieces of equipment, [00:19:16] Speaker 01: BGC just went ahead and ordered them on the open market without following up, without requesting anything from the contracting officer, without doing anything further. [00:19:32] Speaker 01: Now, I also want to point out Mr. Johns spoke to the Windsor case. [00:19:40] Speaker 01: And in that case, there is a big difference between the contract there and the contract here as we pointed out in our briefing. [00:19:49] Speaker 01: The contract in winter had an unless clause that as Chief Judge Prost, then Judge Prost pointed out in dissent in winter, that unless clause expressly permits a ratification theory of liability. [00:20:05] Speaker 01: We do not have a similar unless clause here. [00:20:08] Speaker 01: Instead, what the contract says here is unequivocally, if there is no order or directive issued and signed by the contracting officer, then there will be no adjustment in the contract price. [00:20:23] Speaker 01: That simple contract term with no and less clauses that permit ratification after the fact, that simply does not allow a theory of ratification. [00:20:38] Speaker 01: Your Honor, there is a breach of contract claim here as well, plotting the alternative. [00:20:44] Speaker 01: And BGP conceded that there cannot be a breach of contract for the reduction of GFE. [00:20:51] Speaker 01: There is an allegation that there is a breach of contract because the government did not provide an equitable adjustment. [00:20:59] Speaker 01: But as the trial court correctly found, that claim, that cause of action rises and falls with the equitable adjustment claim. [00:21:08] Speaker 01: If the equitable adjustment is found not to have been a requirement here, in other words, if the court finds that DGT is not entitled to an equitable adjustment, then there can be no breach of contract for a failure to provide an equitable adjustment. [00:21:28] Speaker 01: If there are no further questions, I would like to thank the court and ask again that the court affirm the trial court's decision. [00:21:36] Speaker 01: Thank you. [00:21:37] Speaker 02: Thank you. [00:21:38] Speaker 02: Mr. Johns, rebuttal time, please. [00:21:41] Speaker 00: Thank you, Your Honor. [00:21:42] Speaker 00: Just a few points in the few minutes that I have. [00:21:47] Speaker 00: Again, this Court is reviewing de novo the sufficiency of the complaint, the First Amendment complaint, and in fact, the factual allegations in the complaint speak for themselves. [00:22:01] Speaker 00: It was the contracting officer, Mr. Stefano, as alleged, [00:22:05] Speaker 00: who removed the equipment from the contract, removed it from being made available to VGT, and did so without a written modification to the contract. [00:22:20] Speaker 00: And so, for the government's position at this stage to continue, it would have to imply that a contracting officer, as long as they don't put it in writing, [00:22:34] Speaker 00: plenipotentiary powers that for which the contractor has no remedy based on the changes clause strictly on its face. [00:22:45] Speaker 02: Again, that's just... In other words, your argument is the government didn't do what it was obligated to do when it was decreasing the amount of government furnished property and now you're being penalized for the government's failure to issue a written notice. [00:23:01] Speaker 02: in order to get equitable adjustment, right? [00:23:03] Speaker 02: Is that your argument? [00:23:05] Speaker 02: Yes. [00:23:05] Speaker 00: Yes, Your Honor. [00:23:09] Speaker 00: So again, the allegations are in the complaint. [00:23:13] Speaker 00: The allegation is that the contracting officer directed the BGT only to speak with Ms. [00:23:18] Speaker 00: Oneste, the contracting representative, and that it was Mr. Stefano's decision to divert that equipment. [00:23:28] Speaker 03: What do you say to Mr. Kushner's argument that the contractor should have gone back and insisted on an order from the contracting officer with respect to the withdrawal of the government furnished equipment? [00:23:49] Speaker 00: Well, two things, Your Honor. [00:23:51] Speaker 00: First of all, the contractor continued with the, continued to build the system and provide it on time because, number one, they're a good contractor, and number two, they don't want to be held for default for schedule. [00:24:08] Speaker 00: They don't want to be held for default of contract if they don't deliver this assembled equipment. [00:24:14] Speaker 00: So I think that that's first and foremost, and second of all, [00:24:17] Speaker 00: the contractor was relying on the government acting in good faith and following the clauses. [00:24:26] Speaker 00: Please, please answer. [00:24:27] Speaker 00: I apologize, Your Honor. [00:24:30] Speaker 00: So I believe that those are the two reasons that the contractor had a contractual requirement to continue working and, you know, to complete the project, and yet he had a [00:24:45] Speaker 00: and obligation, I guess, as a matter of business ethics to complete the job for which they were contracted as well. [00:24:54] Speaker 03: Let me ask you one follow-up question, if I could, on that. [00:24:58] Speaker 03: This is based on your experience as dealing with government contracts. [00:25:05] Speaker 03: Suppose that the contractor had followed the advice that Mr. Kushner gave [00:25:12] Speaker 03: which is to go back and insist that the contracting officer specifically and in writing authorize the withdrawal of government furnished equipment. [00:25:21] Speaker 03: And suppose that the contracting officer's representative, whoever it was, said no, I'm in charge of this and you've got your directive that we're going to withdraw the equipment. [00:25:39] Speaker 03: And suppose then, [00:25:42] Speaker 03: upon having been told that the contracting officer was not going to provide any express authorization, that the contractor decided simply to walk off the job because it was not given the assurance that it needed under the contract that it would get an equitable adjustment for the withdrawal of the GFE. [00:26:01] Speaker 03: Do you think that would be chargeable as a default against the contractor? [00:26:10] Speaker 03: Yes, Your Honor, and termination for default is, frankly, to use a colloquial... I know it's a death penalty in this situation, but my question really is, do you think the government would have a strong case for termination for default in that situation? [00:26:31] Speaker 00: They would have a case because the contractor still has an obligation to continue work [00:26:38] Speaker 00: while disputes with the government are adjusted. [00:26:43] Speaker 00: So there were no choices. [00:26:46] Speaker 00: Okay, thank you. [00:26:49] Speaker 02: Okay, thank you. [00:26:51] Speaker 02: We thank both sides and the case is submitted.