[00:00:01] Speaker 00: The United States Court of Appeals for the Federal Circuit is now open and in session. [00:00:06] Speaker 00: God save the United States and this honorable court. [00:00:12] Speaker 01: Thank you. [00:00:12] Speaker 01: Good morning, everyone. [00:00:14] Speaker 01: The first argued case this morning is number 191683, Kellogg Brown and Root Services against the Secretary of the Army. [00:00:23] Speaker 01: Mr. Ho, proceed. [00:00:26] Speaker 04: Good morning, your honors, and may it please the court [00:00:30] Speaker 04: This case is about a contractor who, on very short notice, arranged to supply desperately needed living trailers to troops in Iraq in the early stages of the war. [00:00:42] Speaker 03: Mr. Howe, let's assume you're right about the government's obligation to provide security, that that obligation was breached and that you have damages if you can prove them. [00:01:00] Speaker 03: My problem here is to use the jury verdict method, which is what you say ought to be used. [00:01:08] Speaker 03: There has to be proof that no other method is available. [00:01:13] Speaker 03: And I don't see that that has been done here. [00:01:17] Speaker 03: I don't see that you have shown the inability to get cost data from your subcontractor or in some other way to do what is usually done [00:01:29] Speaker 03: to prove damages in cases like this. [00:01:33] Speaker 03: Could you address that, please? [00:01:35] Speaker 04: Certainly, Your Honor. [00:01:36] Speaker 04: Thank you for the question. [00:01:38] Speaker 04: I think the court's instructions and decision of the Delco electronics decision is instructive on that point. [00:01:50] Speaker 04: In Delco, the contractor did not. [00:01:55] Speaker 03: Please, I'm going to ask you a question about the record in this case. [00:01:59] Speaker 03: Please tell me what it is that you did to attempt to prove damages so that I can understand whether you have shown that there is no other method available. [00:02:11] Speaker 04: Well, the method that was used, and I will speak about the delay claim, the method that was used was to develop a delay day model. [00:02:24] Speaker 04: There were actually five models that were presented to the board, one by the government. [00:02:29] Speaker 04: And then secondly, to apply to those delay days a price that was developed from the marketplace to assess the value of a delay day or a value of a day that the trucks were not moving. [00:02:51] Speaker 03: What is the data that is used to show what you call the price? [00:02:58] Speaker 03: I mean, you would have thought that there would be evidence as to how many trucks there were, how many days they had to sit idle. [00:03:07] Speaker 03: But we don't have that, right? [00:03:11] Speaker 04: Well, there were models. [00:03:14] Speaker 04: Estimates are often used in REA requests for equitable adjustment. [00:03:19] Speaker 04: So it was a modeled estimate. [00:03:23] Speaker 04: The dollar value applied to those delay days was [00:03:27] Speaker 04: based upon information that was provided by the subcontractor and vetted by KBR, given its experience in theater. [00:03:36] Speaker 04: Originally, the subcontractor proposed a $500 a day figure. [00:03:43] Speaker 04: KBR checked with its sources, other subcontractors, its own experience, and determined that was excessive, and brought that down to an agreed $300 per day. [00:03:57] Speaker 02: What was the basis of that $500 a day proposal, the factual basis? [00:04:06] Speaker 04: Your Honor, candidly, it came from FKTC, and it was based on, I believe, their experience. [00:04:15] Speaker 04: I think the important point is that the $300 that KBR determined would be the basis for the settlement [00:04:23] Speaker 04: was based on their own experience, their own vetting of those numbers, their own checking with others. [00:04:30] Speaker 03: What was done? [00:04:31] Speaker 03: What was done? [00:04:32] Speaker 03: Where is it? [00:04:34] Speaker 02: Mr. Ho. [00:04:35] Speaker 02: Yes. [00:04:35] Speaker 02: Can you hear me? [00:04:37] Speaker 04: I can. [00:04:38] Speaker 02: Yes. [00:04:39] Speaker 02: Then don't talk while I'm talking. [00:04:42] Speaker 04: Oh, I'm sorry. [00:04:42] Speaker 04: I heard another judge break in. [00:04:45] Speaker 04: I apologize. [00:04:47] Speaker 02: Mr. Ho, you say candidly it was based on their own experience. [00:04:53] Speaker 02: Candidly, you don't have any factual knowledge in the record, do you? [00:05:01] Speaker 04: In the record, as I said, the price was vetted by KBR given its own experience. [00:05:10] Speaker 04: If you want to call that an estimate, it's an estimate. [00:05:14] Speaker 04: It's based on actual experience. [00:05:17] Speaker 02: You're not answering my question, Mr. Hope. [00:05:19] Speaker 02: Please listen. [00:05:21] Speaker 02: the subcontractor provided no factual basis for its $500 day estimate, did it? [00:05:30] Speaker 04: I don't believe it did. [00:05:32] Speaker 04: It was a claimed number. [00:05:35] Speaker 02: In the private security opinion on page 19 of the blue brief, KBR asserts that we, quote, recognize that timely force protection [00:05:49] Speaker 02: was an essential element of the government's contractual promise to provide military escorts to KBR and its subcontractors under Log Cap 3." [00:06:04] Speaker 02: Where in private security did we address and decide the issue of whether timely force protection was an essential element of Log Cap 3? [00:06:12] Speaker 02: Because I can't find it. [00:06:15] Speaker 04: The Board of Contract Appeals Armed Services Board made that finding, and you're correct. [00:06:24] Speaker 04: Your court did not address that issue because it was not appealed by the government, but you did affirm the court's case. [00:06:33] Speaker 02: Mr. Ho, so your statement on page 19 is incorrect, is it not? [00:06:38] Speaker 04: We attempted to make that distinction, and if it isn't precisely stated, I apologize for that. [00:06:46] Speaker 04: But the actual fact is that your board accepted the ASPCA decision, although that issue was not before it. [00:06:54] Speaker 04: But the underlying finding of the ASPCA was that there was a material breach [00:07:00] Speaker 01: And Mr. Howard, it must be clear that what's bothering us is the absence of precision in all of this. [00:07:09] Speaker 01: And I think it's not in dispute that there was some sort of breach because there was certainly an obligation to provide security that wasn't provided. [00:07:19] Speaker 01: Did the government propose an audit of any sort of the [00:07:27] Speaker 01: numbers that were eventually provided after KBR and the subcontractors negotiated the final price, which, as I understand it, KBR paid the subcontractors. [00:07:44] Speaker 01: Was there any government audit or request for audit in the course of your claim for reimbursement? [00:07:53] Speaker 04: Yes, there was, Your Honor. [00:07:55] Speaker 04: The government did review [00:07:57] Speaker 04: the settlement reached by KBR with its subcontractor. [00:08:02] Speaker 04: Its objection was that the settlement was not based upon actual cost data, but rather was based upon pricing data. [00:08:14] Speaker 04: And I just quickly refer once again to the Delco Electronics case. [00:08:20] Speaker 04: That was the facts in those case. [00:08:22] Speaker 04: The government objected there because there was not cost of pricing data to support a change. [00:08:27] Speaker 04: Judge Margolis at the Court of Federal Claims said that was only one factor to consider in determining a jury verdict. [00:08:38] Speaker 03: That case is unpublished, correct? [00:08:41] Speaker 04: I believe that's true, Your Honor, yes. [00:08:43] Speaker 03: So it's not binding on us? [00:08:46] Speaker 04: That would be true. [00:08:48] Speaker 01: Well, just to try and figure out the [00:08:51] Speaker 01: the reasoning and whether at some point the government's action was reasonable or not reasonable as I recall the record first. [00:09:01] Speaker 01: At least they offered to pay a portion of what was requested and then eventually said no, we're not going to pay anything which doesn't seem particularly reasonable. [00:09:13] Speaker 01: other than their apparent concern as to where these numbers came from. [00:09:20] Speaker 01: And so that's really what I'm trying to understand as to what the obligation might have been on the government or on KBR to go beyond the round number that the negotiation produced. [00:09:41] Speaker 04: Well, I think, Your Honor, points to an important fact, and that is that the contracting officer did determine it was fair and reasonable to pay KBR $25 million for the subcontractor settlement and was open to receiving more information. [00:10:00] Speaker 04: That was subsequently withdrawn. [00:10:01] Speaker 04: Actually, the payment was made, and that it was subsequently withdrawn after, I think, DCAA [00:10:11] Speaker 04: indicated it was concerned that it was not based on cost and pricing data. [00:10:17] Speaker 03: What does the record show about the basis for the $300 estimate? [00:10:24] Speaker 04: It shows that KBR vetted that number with its past work in theater and got some advice from others who were knowledgeable. [00:10:39] Speaker 04: on convoys in the area and determine that that was a reasonable price. [00:10:47] Speaker 04: $500 not reasonable, $300 was reasonable. [00:10:51] Speaker 02: So if you... This is Judge Wallach. [00:10:53] Speaker 02: I have some questions about the FKTC subcontract. [00:10:58] Speaker 02: The FKTC subcontract provided that if FKTC was delayed by the Army or KBR's failure to perform, [00:11:07] Speaker 02: It would be entitled to an equitable adjustment either in compensation or time or both if the delay substantially increased the cost to FKTC or the time that its equipment and forces are required at the site. [00:11:25] Speaker 02: Accordingly, the way I read it, FKTC was entitled to an equitable adjustment only if the Army failed to perform its obligations [00:11:35] Speaker 02: pursuant to Change 5. [00:11:37] Speaker 02: Am I correct on that? [00:11:39] Speaker 04: I think that's a correct statement, Your Honor. [00:11:41] Speaker 04: Yes. [00:11:42] Speaker 02: OK. [00:11:42] Speaker 02: So Change 5 provided, in relevant part, that the Army would provide for the security of the contractor personnel in convoys and on-site commensurate with the threat and in accordance with the applicable theater anti-terrorism force protection guidelines. [00:12:03] Speaker 02: Right? [00:12:04] Speaker 03: Correct. [00:12:06] Speaker 02: And KBR included similar language in the FKTC subcontract, right? [00:12:12] Speaker 04: Correct. [00:12:14] Speaker 02: As far as I can tell, nothing in Change 5 or the FKTC subcontract identified a specific time by which the Army was obligated to place trailers into convoys. [00:12:27] Speaker 02: Am I right? [00:12:30] Speaker 04: There was no express [00:12:32] Speaker 04: time in the force protection clause, which is the language the board used. [00:12:38] Speaker 04: But the contract taken as a whole called for delivery of trailers on a specific date and at the same time promised delivery of force protection. [00:12:51] Speaker 04: Within those two provisions, there was an obligation, a promise by the government to deliver force protection. [00:12:58] Speaker 04: to allow the contractor to meet that very specific delivery date? [00:13:03] Speaker 02: The Army was faced with a whole bunch of logistical problems at that time. [00:13:10] Speaker 02: Am I right about that? [00:13:12] Speaker 02: Yes, they were, Your Honor. [00:13:14] Speaker 02: And KBR appreciated that and had expressed current concerns about it in the time before executing change five, right? [00:13:26] Speaker 04: That's in the record, yes, Your Honor. [00:13:30] Speaker 04: OK. [00:13:31] Speaker 02: And if I, excuse me. [00:13:32] Speaker 02: Well, no, no. [00:13:34] Speaker 02: It's in the record. [00:13:36] Speaker 02: And it's also in the record that there were not sufficient escort vehicles or shooters being made available by the Army. [00:13:46] Speaker 02: That was KBR's position. [00:13:51] Speaker 01: I think that's not disputed by the government. [00:13:58] Speaker 04: No, they did not dispute that. [00:14:03] Speaker 04: That was in the board decision. [00:14:04] Speaker 04: If I may, however, this is a, as we view it, a contract case. [00:14:10] Speaker 04: And looking at the contract, just at the contract, the plain meaning of the contract, it set a priority for these living trailers. [00:14:21] Speaker 04: That was the very first in the statement of work, the very first [00:14:25] Speaker 04: service that is mentioned in there, and it goes into detail. [00:14:30] Speaker 04: It's the only service in those contracts that had a specific date shorter than the original date. [00:14:37] Speaker 04: So if you just look at the... Mr. House. [00:14:40] Speaker 02: Yes. [00:14:42] Speaker 02: Look again, you've taken me right up to the point where I was going. [00:14:48] Speaker 02: Given everything else the Army needed to fight the war, [00:14:52] Speaker 02: In fact, trailers were a relatively low priority item, isn't that right? [00:14:58] Speaker 02: They needed beans, bullets, mail, fuel, all the logistical things that the Army needs to fight in a combat zone. [00:15:10] Speaker 02: Trailers are nice, but they were not, you're saying they were the highest priority item, and that's just not true, is it? [00:15:18] Speaker 04: Well, Your Honor, I respectfully disagree. [00:15:21] Speaker 04: within the broad scope of fighting a war, none of us would deny what you just indicated. [00:15:31] Speaker 04: However, within the subcontract and the prime contract that set the prices here, set the risks of the parties, the highest priority in that subcontract by its plain language were these trailers. [00:15:47] Speaker 04: Now, that was true at the time the subcontract was entered into. [00:15:51] Speaker 04: Subsequently, yes, conditions changed. [00:15:55] Speaker 04: But if you stay within the four corners of that contract, the plain meaning of that contract, statement of work begins. [00:16:03] Speaker 04: The very first statement says it's the commander's intent to bed down the troops by the given dates. [00:16:11] Speaker 04: Those dates were far in advance of any other dates for any other services, including food, including ammunition. [00:16:19] Speaker 04: Now, that may not have been a good decision [00:16:22] Speaker 04: but that was implementing General Sanchez's direction to his contract's people. [00:16:28] Speaker 04: That was the basis for which the contract was entered into. [00:16:31] Speaker 04: Yes, the government can change its priorities and expect to do so, but it has contractual consequences. [00:16:39] Speaker 04: They can't, you know, it can't be a contract that says deliver these services and I'm not going to give you a date when you're going to be able to do that. [00:16:51] Speaker 04: You know, you'll just have to ride, you know, go with the flow. [00:16:56] Speaker 04: You could have a contract like that, I suppose, but that was not this contract. [00:17:00] Speaker 04: And I see I'm well over my time here, so unless there are other questions, I'll stop here. [00:17:07] Speaker 01: Well, let's see. [00:17:08] Speaker 01: Any more questions from the panel at this moment? [00:17:10] Speaker 01: Will we preserve the rebuttal time? [00:17:14] Speaker 02: This is Judge Wallach, not at this time. [00:17:16] Speaker 01: Okay. [00:17:17] Speaker 01: All right, so let's hear from the secretary, Mr. Tyler. [00:17:23] Speaker 00: Thank you, Your Honor, and may it please the court. [00:17:25] Speaker 00: This court should affirm for three independent reasons. [00:17:28] Speaker 03: Mr. Tyler, could you address, please, this question of what the record shows about the basis for this $300 a day estimate and the estimate for the number of days [00:17:41] Speaker 00: Yes, Your Honor, and respectfully, I don't think that the record shows very much. [00:17:45] Speaker 00: I mean, there are certainly models that are used that input that figure. [00:17:50] Speaker 00: However, in terms of specific data, there is no specific actual cost data in the record to support that this is actually what was paid for the trucks for the drivers. [00:18:02] Speaker 00: So the record shows nothing other than the fact that this is an estimate that KBR thought was reasonable. [00:18:07] Speaker 01: But was there an audit that the government [00:18:11] Speaker 01: At that time when all of this was being worked out and negotiated, participate in saying we need your actual numbers? [00:18:22] Speaker 00: There was a DCAA audit and it resulted in costs being suspended. [00:18:26] Speaker 00: I don't recall whether part of that audit was looking incrementally at the different components of what KBR was billing the government for. [00:18:34] Speaker 00: And I don't know if it got to the micro level of looking at the reasonableness [00:18:38] Speaker 00: certain estimate amounts, however... [00:18:42] Speaker 01: the government relied on, isn't it? [00:18:44] Speaker 01: To say, no, we're not going to pay you anything because we don't like the way you came up with the numbers that you've asked for seems curious and unilateral if they're, or I guess this is a question, whether it is that in terms of the obligation of the government at the time to say we want to know day by day or hour by hour [00:19:08] Speaker 01: what happened to your trailers that weren't able to move, how much it costs to provide your own security, if that's what you did, or whatever else. [00:19:19] Speaker 01: But to say the student costs are a contractor or a subcontractor, anything, we're not going to pay anything. [00:19:26] Speaker 01: I'm just wondering, we need to decide whether that's reasonable in view of the contract. [00:19:35] Speaker 00: Thank you, Judge Newman. [00:19:36] Speaker 00: And I would point you to your decision or the panel's decision on which you were a member in total procurement services. [00:19:43] Speaker 00: And it specifically found that there was a breach. [00:19:45] Speaker 00: However, damages were not warranted because there was no actual cost information to support them. [00:19:50] Speaker 00: So here, going back to your question and looking at what the government viewed when it considered KBR's claim, it didn't just look at the absence of actual costs, although that is the barometer in the context of an REA and the context of a cost plus contract. [00:20:05] Speaker 00: as to what can be billed. [00:20:06] Speaker 00: It also looked at the nature of the contract. [00:20:08] Speaker 00: It's very important to keep in mind here that when DCAA went back and they were looking at what KBR did, they looked at the component prices that KBR paid and they questioned those component prices. [00:20:20] Speaker 01: Breach was admitted. [00:20:23] Speaker 01: That was not before us. [00:20:24] Speaker 01: And there's no question but that there was a several months delay, delay at the border and I got the feeling that there was no dispute as to the disruption and there were undoubtedly necessarily additional costs. [00:20:42] Speaker 01: And the real question is where was the obligation, where was the instruction and the information and the basis for saying therefore, based on I'm not sure what, [00:20:53] Speaker 01: We're not going to pay you anything. [00:20:56] Speaker 00: Yes, Your Honor, and just respectfully, I don't consider a breach to be settled in this case and don't think it can necessarily be imported. [00:21:03] Speaker 01: Is that in dispute as to whether there was a breach? [00:21:06] Speaker 00: For the trailers, yes, there was. [00:21:08] Speaker 00: It is in dispute with respect to the issue in private security. [00:21:12] Speaker 01: Well, there's no question in security. [00:21:14] Speaker 01: Is there any question? [00:21:15] Speaker 01: Is the government saying they provided? [00:21:17] Speaker 01: What I see in the record is, as Judge Wallach mentioned, that the situation changed in terms of available personnel to be diverted to provide security for moving trailers. [00:21:35] Speaker 01: At that time, there was a change in the military need. [00:21:41] Speaker 00: Yes, Your Honor, there is no question in the record, no question at all that the government provided security for every single trailer convoy that moved. [00:21:50] Speaker 00: The only question in this case is the timeliness of the security. [00:21:53] Speaker 00: In private security, the issue was that the government didn't actually provide force protection for the food convoys. [00:22:00] Speaker 00: because the food convoys had to move so quickly that they couldn't wait for the government to provide force protection. [00:22:05] Speaker 00: If food spoils before it reaches the mouth of a soldier, it's useless and performance is impossible. [00:22:11] Speaker 00: But trailers don't spoil. [00:22:13] Speaker 00: So trailers can be delayed and they're not rendered useless by delay. [00:22:18] Speaker 01: Did I hear you say that the provision of force protection on which the delay is based [00:22:26] Speaker 01: didn't happen. [00:22:27] Speaker 01: I don't get that from the briefs of either side. [00:22:32] Speaker 00: Well, the board found as fact, Your Honor, that the government provided convoy support for every single trailer convoy that moved. [00:22:40] Speaker 00: The question before the board was simply whether... When it moved. [00:22:43] Speaker 00: When it moved. [00:22:44] Speaker 00: That is correct. [00:22:45] Speaker 00: The question before the board was simply was, was that movement fast enough? [00:22:49] Speaker 00: And I do want to address a question that you asked a few moments ago before I go into the distinctions between [00:22:54] Speaker 00: this case in private security. [00:22:56] Speaker 00: You mentioned that there was a breach and that we have to operate from that basic assumption and setting aside whether we can see that there was a breach, which we do not concede here, that the breach translates in this case. [00:23:08] Speaker 00: You still have to show that the breach results in some sort of damages. [00:23:11] Speaker 00: that the breach approximately causes damages and that was not possible here based on the facts in front of the board. [00:23:18] Speaker 00: And the reason why it's not possible is because KBR already assumed in the firm fixed price contract that it entered into with First Kuwaiti that there would be some delay. [00:23:28] Speaker 00: And at trial, KBR did not try and disentangle. [00:23:31] Speaker 00: They did not try and show that the contract, the firm fixed price contract that they entered into with First Kuwaiti failed to anticipate any particular level of delay, did not account for delay. [00:23:42] Speaker 00: They didn't show a change in the work that resulted from a delay. [00:23:46] Speaker 00: Their position before the board was that they were entitled to cost for every single day of delay. [00:23:52] Speaker 00: regardless of whether it rose to the level of something that was factored into the firm fixed price or not. [00:23:57] Speaker 00: And if that's the case, then KBR should not have paid a higher firm fixed price to account for delay. [00:24:04] Speaker 00: They have to show a change. [00:24:05] Speaker 00: And in this court's jurisprudence, when you have a firm fixed price contract, and Judge Newman, you were on two panels in cases involving firm fixed price contracts that were fairly recent, the DG 21 versus Mavis case, [00:24:18] Speaker 01: in a lakeshore engineering case in which... Well, they're all on different facts. [00:24:23] Speaker 01: Well, what you come up with on one set of facts certainly shows an attempt to provide uniform law, but when the facts are different, [00:24:34] Speaker 01: It's very difficult to translate it here. [00:24:37] Speaker 01: Of course, what's troubling is that here is a contract that says we want these trailers by Christmas, and we'll provide security, and it wasn't provided, and it sort of seemed to go downhill from there. [00:24:54] Speaker 00: Well, Judge Newman, I agree with you. [00:24:56] Speaker 00: The facts are very important. [00:24:57] Speaker 00: So I want to highlight a couple of facts here that I think are very important. [00:25:00] Speaker 00: Not only did KBR enter into a firm fixed price contract with First Kuwaiti to assume delay risk, they then executed change orders over the duration of that contract that extended the contract without adjusting the cost, without adjusting the scope of the work. [00:25:15] Speaker 00: So by executing that contract, Mr. Ho talks about how the contract has to be looked at. [00:25:20] Speaker 00: This is the contract case. [00:25:21] Speaker 00: Change orders are part of the contract. [00:25:23] Speaker 00: And they interpreted the provisions in the subcontract to mean that when these delays happen, this wasn't a change. [00:25:30] Speaker 00: We're not giving more compensation for it. [00:25:32] Speaker 00: The only time that KBR gave more compensation of First Kuwaiti is when it added trailers to the contract, which it did twice in December of 2003 and April of 2004. [00:25:41] Speaker 03: I failed to see what that has to do with the contract with the US government. [00:25:48] Speaker 03: Let me ask you a question about [00:25:51] Speaker 03: your assertion that this has to be a cost-based claim. [00:25:56] Speaker 03: Where does the contract between KBR and the government say that a claim for amounts paid to the subcontractor have to be calculated on a cost base? [00:26:09] Speaker 03: It would seem to me that the amounts paid to the subcontractor are a cost that KBR incurred. [00:26:18] Speaker 03: And they'd have to show that it was reasonable, but I don't see that the calculation has to be cost-based since the amounts paid by KBR to its subcontractor are, in fact, a cost to KBR. [00:26:35] Speaker 03: What am I missing? [00:26:37] Speaker 00: You're not missing anything in terms of reading the contract, Judge. [00:26:39] Speaker 00: I think that's accurate. [00:26:41] Speaker 00: It is a cost plus contract between KBR and the government. [00:26:44] Speaker 00: Every single cost voucher to the government has to be reasonable. [00:26:48] Speaker 00: And what makes a cost reasonable, especially in the context of an REA, is whether it is actually based on actual cost. [00:26:56] Speaker 03: What makes a cost reasonable in the context of a contract... Well, it's based on actual cost in the sense that this is what they paid to the subcontractor, so that's a cost. [00:27:06] Speaker 00: It's KBR's actual cost, but it's First Kuwaiti's REA. [00:27:10] Speaker 00: And that has to be based on actual cost, too, to be reasonable and reasonable... [00:27:14] Speaker 03: Why? [00:27:15] Speaker 03: Well, I mean, obviously it has to be reasonable, but the only thing I'm challenging is whether it has to be cost-based as opposed to price-based. [00:27:26] Speaker 03: And I'm not seeing where there's a requirement in the KBR government contract that says a subcontractor's claim that is passed on to the government has to be cost-based. [00:27:39] Speaker 00: You're right, Your Honor, and it's a good question, and I appreciate it. [00:27:43] Speaker 00: You hit the nail on the head with respect to the interaction between the government and KBR. [00:27:48] Speaker 00: But with respect to First Kuwaiti and KBR, there are multiple provisions, both contractual and legal requirements for REAs that would inform whether actual costs are required. [00:27:58] Speaker 00: It's important to remember here that there are multiple clauses. [00:28:01] Speaker 00: in KBR subcontract that not only require First Kuwaiti to provide actual costs, but also give KBR access to First Kuwaiti's actual costs. [00:28:10] Speaker 00: And numerous courts have held that when you fail to use leverage, when you fail to comply with basic contract terms like that, the negotiation isn't reasonable. [00:28:18] Speaker 00: The payment of costs under those circumstances are reasonable. [00:28:21] Speaker 03: Did KBR provide any explanation here as to why they didn't get cost data or other data from the subcontractor? [00:28:29] Speaker 00: Not initially, and that's when reasonableness is assessed. [00:28:32] Speaker 00: After the fact, their legal team provided two justifications. [00:28:36] Speaker 00: The first, both of them were rejected by the board. [00:28:39] Speaker 00: The first was that actual costs were not required because this was a commercial item and therefore fell into an exception. [00:28:45] Speaker 00: The second was an assumption that Middle Eastern contractors did not keep cost records. [00:28:50] Speaker 00: Again, the board rejected both of these. [00:28:53] Speaker 00: They rejected the commercial item argument on the basis that this was an REA. [00:29:00] Speaker 03: other data was unavailable from the subcontractor? [00:29:03] Speaker 00: Correct. [00:29:05] Speaker 00: They may do showing that actual cost data was available, if I understand your question correctly. [00:29:10] Speaker 00: They get models from the subcontractor, Your Honor, and those models the board found relied on data that was verifiably inaccurate. [00:29:20] Speaker 00: They had inputs that were contradictory based on KBR's own emails and documentation. [00:29:26] Speaker 00: They found that First Kuwaiti had actual cost and actually had redacted actual cost records instead of providing them to KBR. [00:29:33] Speaker 00: And that all informs the reasonableness because if you don't use the leverage that's given to you, if you just allow a subcontractor to disregard the terms of a subcontract, [00:29:42] Speaker 00: If you don't comply with long-standing requirements, when you're paying an REA, requirements that would have been binding on you had you submitted the same cost to the government, those costs aren't reasonable. [00:29:52] Speaker 00: And that infects the cost that KBR billed to the government. [00:29:55] Speaker 00: The costs have to be reasonable when incurred. [00:29:57] Speaker 00: So if KBR paid something that it later billed the government, and those costs weren't reasonable at the time of payment, they don't become reasonable because they were submitted to the government. [00:30:06] Speaker 02: Mr. Tyler, this is Judge Wallach. [00:30:08] Speaker 02: I want you to back up a little bit. [00:30:11] Speaker 02: Where in the record is that redaction? [00:30:13] Speaker 02: I missed that. [00:30:18] Speaker 00: It appears in two different places, Your Honor, and it's a factual finding, but it's also appears in, so the factual finding is on page nine, finding 27. [00:30:34] Speaker 00: It says, right in the middle of the paragraph, as was the case with its double handling request, FKTC did not base its delay REA upon actual costs. [00:30:43] Speaker 00: For example, the truck leases FKTC submitted redacted the prices FKTC paid for trucks, thereby refusing to disclose its costs. [00:30:51] Speaker 00: I believe the board comes back to that in the discussion section when it's evaluating the reasonableness of the actual cost, but certainly if actual costs were required by the contract, they're required for REAs, and even the term that KBR relies on here, 3.2.5, uses the term equitable adjustment, which is a very specific term of art in contract law and would incorporate everything in a simple contract reading that goes with that term. [00:31:15] Speaker 00: The redaction of actual cost is not reasonable, especially with all those requirements. [00:31:21] Speaker 00: I do want to go back to some points that were raised earlier and specifically, Judge Newman, I believe you raised the contract language and the breach issue. [00:31:31] Speaker 00: I want to be very clear on the contract language in this case when we're evaluating the applicability of private security. [00:31:37] Speaker 00: The contract language is not exactly the same. [00:31:40] Speaker 00: So the force protection clause in change five is the same, but there is in the scope of work section [00:31:45] Speaker 00: additional language, and because the contract has to be read as a whole, that additional language matters. [00:31:51] Speaker 00: It says, it is the commander's intent to rapidly bed down the remainder of CJTF-7 soldiers in accordance with established and provided priorities. [00:31:59] Speaker 00: Now, Mr. Ho said that those priorities were in the contract. [00:32:02] Speaker 00: That is incorrect. [00:32:04] Speaker 00: The board found that those priorities were not in the contract. [00:32:08] Speaker 01: But you're not saying that they should be ignored. [00:32:12] Speaker 01: What I'm really trying to get at here is the government's obligation to do something to audit, to provide an estimate. [00:32:26] Speaker 01: to bring in their own estimators as if the subcontractor is not going to provide cost of trailer figures. [00:32:35] Speaker 01: If that's a factor, I don't think it is, but whatever their payroll might have been as they were waiting at the border for security in order to move as a convoy. [00:32:48] Speaker 01: But to say that never mind you're going to get nothing even though perfectly objectively the contractor KBR worked out with its subcontractors a settlement, a significant reduction in the initial request as from the commercial viewpoint and from the viewpoint of service to the government. [00:33:16] Speaker 01: Of course the services had already been provided. [00:33:18] Speaker 01: to try and figure out just what in the relationships between government and the private sector, what the government's obligation may be, or all the burdens of everything that goes wrong. [00:33:36] Speaker 01: such as a dramatic increase in the military activity, is that burden, if it's not explicitly stated in the contract, to be not considered at all? [00:33:51] Speaker 00: Yes, Your Honor. [00:33:52] Speaker 00: So I believe the standard, and I think the parties agree that Essex is the standard. [00:33:56] Speaker 00: We think that this is the analysis that the Board did. [00:33:59] Speaker 00: It was evaluating at what point the delay became. [00:34:01] Speaker 00: It crossed the line from something that was just mere delay, anticipated delay, [00:34:06] Speaker 00: that was known to the parties at the time of contract formation and crossed the line to a failure to perform. [00:34:11] Speaker 00: And it is found that that didn't happen for the trailers. [00:34:15] Speaker 01: Your Honor, if I can just ask you... No, please, let's continue until we run out of questions. [00:34:20] Speaker 00: I appreciate that, Your Honor. [00:34:22] Speaker 00: So with respect to the Board's finding, the Board found that this risk that was assumed was in the contract. [00:34:32] Speaker 00: That's a factual finding. [00:34:34] Speaker 00: And I can tell you when you're talking about the interaction between government contractors and the government, what is not reasonable is for the government to pay for the same thing twice. [00:34:44] Speaker 00: And ultimately, that's what this case boils down to. [00:34:46] Speaker 00: If you disagree on the applicability of private security, if you think that that additional contract language doesn't matter, if you think that the party's differing expectations based on that contract language doesn't matter, and you import that breach finding into this case, you still need to find proximate cause and damages. [00:35:03] Speaker 00: And if the costs have already been paid for because they are in the contract, then there is no proximate cause and there are no damages. [00:35:11] Speaker 00: And one of the board's findings that was not contested with any data, KBR quarrels with it on appeal but doesn't provide any indication that it's factually wrong, [00:35:21] Speaker 00: is that this particular risk, the risk that happened, was in the contract. [00:35:25] Speaker 00: And that's not just the government's position. [00:35:27] Speaker 00: That was also KBR's position. [00:35:29] Speaker 00: Because in interpreting the same contract terms in a different contract with a different subcontractor, KBR reached the conclusion that more compensation was not allowable because the risk had already been provided for, already been allocated, the terms precluded additional compensation. [00:35:46] Speaker 00: And regardless of whether there is a delay and, in general, a fairness obligation of the government to come to the table and negotiate ways to fix resolutions, the government cannot pay for the same thing twice. [00:35:57] Speaker 00: It is not reasonable for the government to do that. [00:36:00] Speaker 01: But did they pay for it? [00:36:02] Speaker 01: Many of the briefs say that a request specific to providing private security for the convoys, a request to the government to pay for it, was turned down at the time. [00:36:16] Speaker 00: Yes, Your Honor, and that request was for free. [00:36:18] Speaker 00: KBR, or First Kuwaiti, was willing to provide that security for free, presumably understanding that the delay costs were already in the contract. [00:36:26] Speaker 00: In private security, what the government did is it came in and it tried to break apart a firm fixed price. [00:36:31] Speaker 00: It said that the part that you use to pay private security is not allowable and the rest of it is. [00:36:36] Speaker 00: We're not doing that here. [00:36:38] Speaker 00: For better or worse, we paid that entire firm fixed price. [00:36:41] Speaker 00: The only issue in this case [00:36:43] Speaker 00: indicate your first kawaii have come back for more money nearly over thirty percent more than the original contract value for a delay that as a matter of fact [00:36:53] Speaker 00: the board found was anticipated. [00:36:55] Speaker 00: It was priced into the contract. [00:36:57] Speaker 00: And that's evident from the change orders because every single time the period of performance was extended, there was no compensation that was added. [00:37:05] Speaker 00: There was no change in the sublet work. [00:37:07] Speaker 00: This is exactly what was envisioned. [00:37:09] Speaker 00: And in fact, every single change order referred back to those subcontract terms and conditions. [00:37:14] Speaker 00: It said, for example, in change order one, [00:37:17] Speaker 00: This is in accordance with the subcontract terms and conditions stating that days lost due to convoy support shall not be taken into consideration. [00:37:24] Speaker 00: So they are clearly looking back, they are referencing those prior terms and they are interpreting the contract for us. [00:37:30] Speaker 00: What they're saying is that what happened [00:37:32] Speaker 00: is not a change that warrants more compensation. [00:37:36] Speaker 00: And they do this over the entire life of the contract. [00:37:39] Speaker 00: It wasn't until the contract was over, until the government had already paid all this money, that KBR and First Kuwaiti came back for more. [00:37:46] Speaker 00: And they came back for a lot more. [00:37:47] Speaker 00: They came back for $50 million more. [00:37:49] Speaker 00: And the government doesn't believe, regardless of the applicability of private security, that it's reasonable for the government to pay that cost again. [00:37:56] Speaker 00: And that is the basis on which this court should affirm the board's decision. [00:38:02] Speaker 01: Okay. [00:38:03] Speaker 01: Any more questions from the panel? [00:38:05] Speaker 02: No. [00:38:06] Speaker 02: All right. [00:38:07] Speaker 02: Judge Wallach, no. [00:38:08] Speaker 01: Thank you. [00:38:08] Speaker 01: All right. [00:38:10] Speaker 01: Okay. [00:38:10] Speaker 01: Thank you. [00:38:11] Speaker 01: We'll hear rebuttal from Mr. Ho. [00:38:14] Speaker 04: Yes. [00:38:14] Speaker 04: Thank you, Your Honor. [00:38:16] Speaker 04: I think the one fundamental error that both the board made and the government in its argument, and that is that we've discussed a lot of fact-finding [00:38:28] Speaker 04: about what people thought about the risks, what they thought about the priorities under the contract. [00:38:35] Speaker 04: And only then did the board turn to interpreting the contract. [00:38:39] Speaker 04: But I think this court has made clear the reverse order is required. [00:38:44] Speaker 04: You look at the language of the contract and you determine if it's ambiguous and if it's not ambiguous, you stay with the plain meaning of the contract. [00:38:53] Speaker 04: And we think there was nothing ambiguous in the contract. [00:38:57] Speaker 04: When it came to the government's priorities, the trailers were prioritized over all other priorities in that contract, including ammunition support, et cetera. [00:39:12] Speaker 04: That was the statement in the statement of work that General Sanchez insisted upon. [00:39:21] Speaker 04: FKTC's right to an equitable adjustment for the delays upon a government breach could not be any more clear. [00:39:29] Speaker 04: It's in paragraph 3.2.5. [00:39:34] Speaker 03: And the provisions of the subcontract that have been... What does the record show about why KBR didn't do a better job of coming up with costs and proof of the damage here? [00:39:48] Speaker 03: Does the record show anything as to why you didn't go to the subcontractor and get better data? [00:39:55] Speaker 04: The KBR did go to the subcontractor and it was not able to. [00:40:01] Speaker 03: Why did you accept action of cost data? [00:40:08] Speaker 04: The KBR wanted to move this matter along. [00:40:13] Speaker 04: Pricing data is not a [00:40:15] Speaker 04: you know, is not unacceptable. [00:40:18] Speaker 04: The government uses pricing data all the time in entering into any number of contracts. [00:40:25] Speaker 04: The requirements under the Truth in Negotiations Act is to get cost or pricing data. [00:40:32] Speaker 04: So pricing data is not unacceptable. [00:40:35] Speaker 03: It has been shown to be reasonable, doesn't it? [00:40:39] Speaker 04: It does. [00:40:40] Speaker 04: And KBR demonstrated that by its own vetting of the marketplace [00:40:45] Speaker 04: what a price for a truck idled for a day would bring, you know, any other vendor that would charge a price for that. [00:40:57] Speaker 04: They vetted that and went from the $500 to the $300. [00:41:01] Speaker 03: Do they provide data or just statements that they vetted? [00:41:05] Speaker 04: They testified to that at the hearing. [00:41:10] Speaker 02: This is Judge Wallach. [00:41:14] Speaker 02: Does the record show anything about KBR's inquiries about the redacted data from the sub, 1st Kuwaiti? [00:41:30] Speaker 04: I do not believe so, Your Honor, but I can check and provide that later if that's appropriate. [00:41:40] Speaker 01: Yes, please continue if there's more to be covered. [00:41:44] Speaker 02: Well, this is Wallach again. [00:41:48] Speaker 02: My concern is I hadn't noticed the redacted data matter. [00:41:53] Speaker 02: And it seems to me that prime, first it would be natural for KBR to say to First Kuwaiti, hey, wait a minute. [00:42:07] Speaker 02: Tell us what this is. [00:42:09] Speaker 02: But since I didn't see that, I didn't further look [00:42:13] Speaker 02: to see whether there was anything. [00:42:16] Speaker 02: And I guess you're telling me that you don't have it at your fingertips. [00:42:21] Speaker 04: I do not, Your Honor. [00:42:26] Speaker 04: Okay. [00:42:26] Speaker 04: Just a couple of other points in rebuttal. [00:42:32] Speaker 04: Council has made reference to a series of contract changes, subcontract changes that pushed out the [00:42:42] Speaker 04: date for delivery of the trailers as an indication of an understanding of the risk that it had undertaken. [00:42:50] Speaker 04: I don't think that's accurate. [00:42:53] Speaker 04: Contractors, prime contractors, will often modify, you know, subcontracts to take a contractor out of technical default. [00:43:04] Speaker 04: And obviously KBR and FKTC didn't understand that they were [00:43:11] Speaker 04: giving up or acknowledging that these unexpected delays would not be compensable. [00:43:20] Speaker 04: Council mentioned the Essex case as having been adopted by the board to determine what was a reasonable time period within which the government would provide the force protection. [00:43:34] Speaker 04: The board never mentions the Essex case in its decision [00:43:40] Speaker 04: I know there's been an attempt to bring together the fact findings that the board did make to, after the fact, assume that the board was thinking about some reasonable date. [00:43:55] Speaker 04: But the board said there was no date for delivery of forest protection. [00:44:02] Speaker 04: And the contract of that nature, [00:44:05] Speaker 04: You know, we believe would not be a contract that's unenforceable. [00:44:09] Speaker 04: A promise with no date to deliver on the promise is not a promise at all. [00:44:15] Speaker 04: And I think finally it was mentioned that there are multiple clauses in the contract documents, particularly the subcontract that required FKTC to produce cost data. [00:44:30] Speaker 04: The only provision in the subcontract that refers [00:44:35] Speaker 04: Cost data is the changes clause in the subcontract. [00:44:41] Speaker 04: And as a matter of law, government contract law, there is a difference between a change and a government delay. [00:44:51] Speaker 04: They are typically covered under different clauses. [00:44:55] Speaker 04: You can have delay associated with the change. [00:44:59] Speaker 04: But what we have here is pure delay. [00:45:01] Speaker 04: There was no change in the contract. [00:45:03] Speaker 04: It was a pure delay of delivery of government-promised force protection. [00:45:09] Speaker 04: So that language in the changes clause, which is the only one that refers to cost data, is not really on point. [00:45:19] Speaker 04: And I guess, again, finally, discussion about what was assumed in the price that FKTC charged [00:45:31] Speaker 04: for its services, once again, I think we have things in reverse. [00:45:38] Speaker 04: One needs to look first at the four corners of the subcontract document. [00:45:43] Speaker 04: The document did address, in three places, it addressed delay. [00:45:49] Speaker 04: One was that FKTC would be entitled to both time and money in the event the government breached its obligations, which we say it did here. [00:46:01] Speaker 04: The other two provisions were provisions 4.1 and 4.2, and neither of those deal with a government breach. [00:46:13] Speaker 04: 4.1 talks about delays in KBR convoy coordination and support. [00:46:23] Speaker 04: That was KBR coordination. [00:46:24] Speaker 04: Obviously, KBR had a role in coordinating the convoys, [00:46:29] Speaker 04: That provision says nothing about a government failure to perform its obligations. [00:46:34] Speaker 04: And then finally, the other provision in the subcontract is Section 4.2, which talks about the subcontractor FKTC taking responsibility if the contractor, FKDR, needed to make adjustments in working hours, manpower, equipment deemed necessary by the contractor. [00:46:58] Speaker 04: Again, I think that's a far cry from assuming the risk of government breach of its prime contract obligations. [00:47:07] Speaker 04: And if there are no further questions, I thank the court. [00:47:11] Speaker 01: Any more questions from the panel? [00:47:14] Speaker 04: Judge Wallach, no. [00:47:15] Speaker 01: No. [00:47:16] Speaker 01: OK. [00:47:17] Speaker 01: Thanks to counsel. [00:47:18] Speaker 01: The case is taken under submission.